WH
WO-4455 · Northmoor Civils

Steel walkway + handrail

Salford Quays deck · qty 1 · S275 + CHS

due Delivered 21 Jul
Revision-locked · Drawing NGF-4455, Rev B. Only the current rev can be issued to the floor.Rev A superseded
Progress
100%
Hours est / act
110 / 116
Job value
£12,600
Exec class
EXC2 · EN 1090
Routing · digital traveller9 operations
OP 10Programme / nestDone
Programming / Nest · Lantek + Inventor (read)Gary Holtest 8h · act 8.8h ▲
OP 20Tube laserDone
Tube Laser · RVD tube laserMick Bardsleyest 14h · act 15.5h ▲
OP 30Plasma cutDone
Plasma · Kerf plasmaDave Sutcliffeest 10h · act 11h ▲
OP 40BendDone
Press Brake · Amada 100-tonDave Sutcliffeest 12h · act 16h ▲
OP 50Fit-upDone
Fit-up Bay · Fitting benchTom Pillingest 24h · act 27h ▲
OP 60Weld to WPSDone
Weld Bay 1 · MIG/MMA bayAndy Kershawest 30h · act 31.5h ▲
OP 70Galvanise (subbed)Done
Galvanising (sub)est 0h · act 0h
OP 80QCDone
Inspection · QC benchWilliam Huntest 4h · act 4h
OP 90Dispatch / installDone
Dispatch / Install · Yard + install teamest 12h · act 12h
Every line here was a scan at the kiosk — badge → job → operation. Nobody walked the floor or totted hours on a scrap of paper.